Closing the office for a renovation is often not an option. Clients still call, staff still need desks and the lease still gets paid. The good news is that most office renovations can be done in phases while the business keeps running. It takes more planning up front, and that planning is what this guide covers.
Plan phases around how your team works
Start by mapping the office: who sits where, which rooms are used every day and which can be emptied for a while. Then split the work into phases so one area is under construction while the rest stays usable. Meeting rooms and storage are often the easiest to do first, which gives you somewhere to move people when their area is next. Agree on the phases with your landlord too, especially if common areas, washrooms or base building systems are affected.
After-hours and weekend work
The noisiest and dustiest work, such as demolition, cutting and drilling into concrete, can be scheduled for evenings or weekends. It usually costs more per hour, so we use it where it matters most and do quieter work during the day. Check the building’s rules on working hours, elevator use and deliveries before the schedule is fixed.
Dust, noise and safety
- Sealed dust barriers and zipper doors between the work area and your team.
- Protected floors and walkways along the route crews use.
- Clear signage and a separate entry for crews where the space allows.
- Fire exits and paths kept open at all times.
- A clean-up at the end of every shift so the space is usable in the morning.
Keeping IT and phones running
Network cabling, the server or comms room and power to workstations are the parts that can stop a business. Bring your IT provider in early. Plan any shutdowns for after hours, label everything before it is moved, and test the connections before staff return to a finished area.
Telling staff and clients what to expect
Share a simple schedule with your team: which area is closed, when and where they move to. Tell clients who visit in person about any change of entrance or meeting space. A short heads-up email prevents most complaints.
A sample phased schedule
- Phase 1: meeting rooms and storage, with temporary desks set up in the open area.
- Phase 2: the first half of the open office; staff move into the finished meeting rooms.
- Phase 3: the second half of the office.
- Phase 4: reception and common areas, done after hours, then a final clean.
The real phases depend on your layout, the permits and the landlord’s approvals. For the permit side, read our tenant improvement guide.