Office renovation by JMK Construction, Edmonton

How to Renovate Your Office While Staying Open

Closing the office for a renovation is often not an option. Clients still call, staff still need desks and the lease still gets paid. The good news is that most office renovations can be done in phases while the business keeps running. It takes more planning up front, and that planning is what this guide covers.

Plan phases around how your team works

Start by mapping the office: who sits where, which rooms are used every day and which can be emptied for a while. Then split the work into phases so one area is under construction while the rest stays usable. Meeting rooms and storage are often the easiest to do first, which gives you somewhere to move people when their area is next. Agree on the phases with your landlord too, especially if common areas, washrooms or base building systems are affected.

After-hours and weekend work

The noisiest and dustiest work, such as demolition, cutting and drilling into concrete, can be scheduled for evenings or weekends. It usually costs more per hour, so we use it where it matters most and do quieter work during the day. Check the building’s rules on working hours, elevator use and deliveries before the schedule is fixed.

Dust, noise and safety

  • Sealed dust barriers and zipper doors between the work area and your team.
  • Protected floors and walkways along the route crews use.
  • Clear signage and a separate entry for crews where the space allows.
  • Fire exits and paths kept open at all times.
  • A clean-up at the end of every shift so the space is usable in the morning.

Keeping IT and phones running

Network cabling, the server or comms room and power to workstations are the parts that can stop a business. Bring your IT provider in early. Plan any shutdowns for after hours, label everything before it is moved, and test the connections before staff return to a finished area.

Telling staff and clients what to expect

Share a simple schedule with your team: which area is closed, when and where they move to. Tell clients who visit in person about any change of entrance or meeting space. A short heads-up email prevents most complaints.

A sample phased schedule

  • Phase 1: meeting rooms and storage, with temporary desks set up in the open area.
  • Phase 2: the first half of the open office; staff move into the finished meeting rooms.
  • Phase 3: the second half of the office.
  • Phase 4: reception and common areas, done after hours, then a final clean.

The real phases depend on your layout, the permits and the landlord’s approvals. For the permit side, read our tenant improvement guide.

How JMK plans an office renovation

We walk the space with you, learn your hours and busy periods, and give you a phased plan with the quote. See our office construction page and all our commercial renovation services.

LATEST BLOG ARTICLES

Upgrading Home Office Ergonomics For Better Productivity

Tired of back pain and glare in your home office? See how JMK Construction transforms Edmonton and St. Albert workspaces for peak 2026 productivity...

Kitchen Renovation Cost In Edmonton: 2027 Budget Guide

Discover real 2026–2027 pricing breakdowns, cabinetry and countertop costs, City of Edmonton permit rules, and honest insights from local homeowners so you can budget with confidence...

Interlocking Pavers vs Concrete Patios in Edmonton

Both interlocking pavers and poured concrete make good patios in Edmonton. They handle our winters differently, they look different and they age differently. Here is how they compare so you can choose...

Deck Permits in Edmonton: What You Need Before Spring

Thinking about a new deck this spring? In Edmonton, most decks need a permit, and the permit is the part that takes time. Planning it over the winter means you can build as soon as the ground allows...