“How long will it take?” is the second question everyone asks, right after cost. The honest answer depends on the size of the job, the permits and how fast selections get made. What doesn’t change is the order. Here is how a renovation runs in Edmonton, from first visit to final inspection, and where the waiting usually happens.
1. Walk-through and quote
We visit, look at the space and what’s behind the walls where we can, and talk through what you want. You get a written quote listing what is included. The faster you can share photos, measurements and a rough budget, the faster this step goes.
2. Design and selections
Layout, cabinets, tile, fixtures, flooring and lighting. This is the step homeowners most often underestimate. Late changes to selections are the most common reason a renovation schedule slips, so we try to lock the big items (cabinets, windows, special-order tile) before demolition.
3. Permits
Many renovations need a permit from the City of Edmonton, including finishing a living space, bedroom or bathroom, and changing window or exterior door sizes (City of Edmonton: renovations and basement development). Electrical and plumbing work often goes on the same application. The City publishes current processing times on its site, and inspections can only be booked once the permit is issued (Booking an Inspection). For basements, see our basement permits guide.
4. Demolition and rough-in
Once the permit is in hand: demolition, then framing, plumbing, electrical and HVAC rough-in. Surprises live here: old wiring, water damage, out-of-level floors. We flag anything we find before we fix it, with the cost.
5. Inspections and finishing
Rough-in inspections happen before the walls close. After they pass: insulation, drywall, paint, flooring, cabinets, tile and trim. Each trade is responsible for booking the inspection for its own discipline, and we coordinate the order so nobody waits on someone else.
6. Handover and warranty
Final inspection, a walkthrough with you, and a list of anything that still needs a touch-up. We fix the list before we call the job done, and you get the paperwork for the permit and any product warranties.
Want your own schedule?
Every house is different. Book a walk-through and we will give you a schedule for your project, stage by stage. Related: full home renovation, basement development, kitchen renovation.